Alagoas Histórico

Complete shutdown of rock salt extraction

In May 2019, rock salt extraction in Maceió was completely ceased, consequently halting production at the Maceió plant. This partially affected the operation of the PVC plant in Marechal Deodoro and operations at the Camaçari Complex in Bahia. Despite the shutdown, Braskem committed not to make layoffs, involving the team in maintenance services and professional training programs.

In early 2021, the factory resumed operations with salt acquired from Chile. The operations involve over 60 companies, employing more than 12,000 people, including 750 direct employees of Braskem and 3,300 subcontractors.

The definitive closure of the wells has been underway since November 2019 when Braskem presented measures to the Brazilian National Mining Agency (ANM) to definitively cease salt extraction and close and fill wells in Maceió, prioritizing safety.

Braskem supplied the necessary resources and the entire planning for accomplishing the said efforts in concert with the Civil Defense and other authorities.

See where the 35 deactivated wells are located:

P01
P02
P03
P04
P05
P06
P07
P08
P09
P10
P11
P12
P13
P14
P15
P16
P17
P18
P19
P20
P21
P22
P23
P24
P25
P26
P27
P28
P29
P30
P31
P32
P33
P34
P35
Icone mão

Click on the location to see the information.

Wells 1 to 35: permanently deactivated